How to measure for concrete
For a slab, measure the inside length and width of the formwork and the depth you will pour. Measure depth in several places, because excavations are rarely level, and use the average. Remember that any sub-base of compacted hardcore or gravel is not concrete and should not be counted.
For a strip footing, add up the length of every trench run. Where two trenches meet at a corner, count the overlap only once. Enter the width of the trench and the depth of concrete, not the full depth of the trench if some of it will be backfilled.
For post holes, enter the hole diameter and the depth that will be filled with concrete. A useful guide is a hole about three times the width of the post and one third to one half of the post's above-ground height deep, but follow the depth your local frost line and building rules require.
How the concrete calculation works
slab or footing volume = length × width × depth
post hole volume = holes × (π × (diameter ÷ 2)² × depth − post width² × depth)
total = volume × (1 + waste %)
bags = total ÷ yield per bag, rounded up All measurements are converted to metres (or feet) first, so mixing centimetres and metres, or inches and feet, is handled for you. Imperial results are shown in cubic yards, the unit ready-mix suppliers use, and cubic feet, the unit printed on bags. Bag yields are based on a typical dry mix: 0.30, 0.45 and 0.60 cubic feet for 40, 60 and 80 lb bags, and the same density for metric bags.
Worked examples
Shed base: a 3 × 4 m slab, 10 cm thick, is 3 × 4 × 0.10 = 1.2 m³. With 10% extra that is 1.32 m³, or 113 bags of 25 kg. At that size, a small ready-mix delivery is worth pricing.
Patio: a 10 × 10 ft slab, 4 in thick, is 10 × 10 × (4 ÷ 12) = 33.3 ft³, which is 1.23 yd³. Adding 10% gives 1.36 yd³ (36.7 ft³), or 62 bags of 80 lb.
Fence posts: eight 10 in holes, 36 in deep, holding 4×4 posts (3.5 in actual size) need about 1.38 ft³ each once the post is subtracted. With 10% extra that is 12.2 ft³, or 21 bags of 80 lb.
Concrete bags for common slab sizes
Including 10% extra. Above about 1 m³ or 1.3 yd³, compare the price of ready-mix.
| Slab | Volume | 80 lb bags | 60 lb bags |
|---|---|---|---|
| 8 × 8 ft, 4 in | 0.87 yd³ | 40 | 53 |
| 10 × 10 ft, 4 in | 1.36 yd³ | 62 | 82 |
| 10 × 10 ft, 6 in | 2.04 yd³ | 92 | 123 |
| 12 × 12 ft, 4 in | 1.96 yd³ | 88 | 118 |
| 10 × 20 ft, 4 in | 2.72 yd³ | 123 | 163 |
| 20 × 20 ft, 4 in | 5.43 yd³ | 245 | 326 |
| Slab | Volume | 25 kg bags | 40 kg bags |
|---|---|---|---|
| 2 × 2 m, 10 cm | 0.44 m³ | 38 | 24 |
| 3 × 3 m, 10 cm | 0.99 m³ | 85 | 53 |
| 3 × 4 m, 10 cm | 1.32 m³ | 113 | 71 |
| 4 × 4 m, 10 cm | 1.76 m³ | 151 | 94 |
| 3 × 3 m, 15 cm | 1.49 m³ | 127 | 80 |
| 5 × 5 m, 10 cm | 2.75 m³ | 235 | 147 |
Common mistakes
- Using nominal lumber sizes. A "4×4" post is 3.5 × 3.5 in, and a "6×6" is 5.5 in.
- Confusing bag weight with yield. Two 40 lb bags make the same volume as one 80 lb bag; the weight is what matters, not the number of bags.
- Forgetting the thickened edge. Many slabs have a deeper perimeter. Calculate it as a footing and add it on.
- Tiling straight onto fresh concrete. New slabs need weeks to cure before tiling; when the time comes, size the job with the tile calculator.
- Ordering exactly. Running out mid-pour is far worse than a few leftover bags, which keep for months if stored dry.